Ashburn, VA
Data Center Building Additions
Overview
This project encompassed site work for two building additions on a busy data center campus. A key element was the installation of a 792-foot-long box culvert through the site, consisting of more than 100 individual 6'x5' precast sections. The team completed the installation in under two weeks with detailed planning and coordination.
SERVICES PROVIDED
Clearing
Excavation and grading
Drilling and Blasting
Stormwater management
Wet utility installation
Stone installation
Site concrete
Asphalt paving
More Projects